The Caldwell Place Project
:::ATTENTION:::
Caldwell Place Project Update
As of today the township has now received an update on what we are calling the “Caldwell Place Project.” After an initial set of dates were sent out for the start of this project below are the actual up to date details on the new start dates of the project. The administration will be keeping a close eye on this project and we hope to be able to give you more updates as they come in.
9/3 Caldwell Place Closed for Test Pits to be performed and depending on the findings in these test pits they will then move onto the start of the project or Phase One. Time frame for pit work is one day.
9/15- 9/26 Phase One of the project is to begin and below is a full explanation of what this project will look like….
:Summary of Caldwell Place Project:
Caldwell Place Project
Caldwell Place from Mountain Ave to Rose Ave will be closed during this project.
The Caldwell Place culvert replacement is a county-led road project that is scheduled to begin with preliminary work. Test pits will be dug to assess the scope of the project. These initial activities will require a temporary road closure.
Following the assessment from the test pits, the New Jersey Water will begin work on both the 12-inch and 8-inch water lines.
PSE&G will follow NJ American water and relocate their gas lines.
Due to the size and complexity of the trench required and the water and gas lines being moved, the road will be closed for two to four weeks in this initial stage of work. At this time, no firm dates have been established for the subsequent phases of the project which will entail closing this section of Caldwell again, and the County will follow with a complete replacement of the culvert starting in the fall. It is estimated that this will require three to four months to complete. As we receive additional information and dates we will update everyone so please follow our socials and website for up to date information.